Planit Charge, in collaboration with Energypro, supplied and commissioned an expanded EV charging system at 1 William Street.

The project ensured the site’s infrastructure was upgraded with high-quality Schneider equipment, integrated load management, and full metering capability to support the growing adoption of electric vehicles.

Scope of Works

  1. Supply of Equipment
    - Provision of four (4) Schneider EVlink Pro AC 22 kW chargers with tethered Type 2 charging cables.
    - Supply of MID-approved meters for each charger to enable accurate energy monitoring and reporting.
    - Supply of all required communications hardware to support integration with the site’s Load Management System (LMS).
  2. Load Management System (LMS) Upgrade
    - Provision of the Schneider LMS licence upgrade to extend system capacity.
    - Supply of updated configuration files and programming to ensure seamless expansion of the charging network.
  3. Commissioning
    - Onsite commissioning of the four chargers, MID meters, and the upgraded LMS.
    - Testing of all communication pathways and verification of correct load management functionality.
    - Integration of the chargers into the existing LMS environment in coordination with Energypro’s electrical installation team.

Outcome

Through the supply of Schneider EVlink Pro equipment and expert commissioning, Planit Charge enabled 1 William Street to expand its EV charging capacity with a robust, fully managed solution, while Energypro delivered the supporting electrical and cabling works.